
Billing Code: 4910-60-P
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
49 CFR 192
Pipeline Safety: Guidance On When The Baseline Integrity Assessment
Begins
AGENCY: Office of Pipeline Safety (OPS), Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT.
ACTION: Notice; issuance of advisory bulletin.
SUMMARY: This document provides guidance to operators of gas transmission pipelines on the requirement in 49 U.S.C. § 60109 that operators begin the baseline integrity assessment of pipeline segments located in high consequence areas no later than June 17, 2004. Trade associations representing natural gas pipeline companies affected by this requirement, have asked for guidance on what actions an operator must take to begin a baseline assessment. This document provides guidance to gas transmission operators on what initial steps PHMSA/OPS expects each operator to take to begin the baseline integrity assessment to meet the intent of the statute.
General
Information
You may contact the Dockets Facility by phone at (202) 366-9329, for copies
of this document or other material in the docket. All materials in this docket
may be accessed electronically at http://dms.dot.gov/search. Once you access
this address, type in the last four digits of the docket number shown at the
beginning of this notice (in this case 7666), and click on search. You will
then be connected to all relevant information.
Anyone is able to search the electronic form
of all comments received into any of our dockets by the name of the individual
submitting the comment (or signing the comment, if submitted on behalf of an
association, business, labor union, etc.). You may review DOT’s complete Privacy
Act Statement in the Federal Register published on April 11, 2000 (Volume 65,
Number 70; Pages 19477 - 78) or you may visit http://dms.dot.gov.
FOR FURTHER
INFORMATION CONTACT: Mike Israni by phone at (202) 366-4571, by fax at (202) 366-4566, or by e-mail at mike.israni@rspa.dot.gov,
regarding the subject matter of this guidance. General information about the PHMSA/OPS programs may be obtained by accessing PHMSA’s
home page at http://www.rspa.dot.gov.
SUPPLEMENTARY
INFORMATION:
I. Advisory Bulletin (ADB-03-07)
To: Operators of gas transmission pipelines.
Subject: The requirement in 49 U.S.C. §60109 (c) that each operator begin the baseline
integrity assessment of segments in high consequence areas no later than June
17, 2004.
Purpose: To provide guidance to operators on what steps PHMSA/OPS considers acceptable
to begin the baseline integrity assessment process to meet the intent of the
statute.
Advisory: PHMSA/OPS will accept the following steps as having begun the baseline assessment
process required by 49 U.S.C. §60109 (c).
Prior to June 17, 2004, each operator must have begun to -
- identify segments that are located in high consequence areas;
- integrate available data on those identified segments;
- prioritize the highest risk segments from available data on those identified
segments; and
- select the assessment method best suited to assess (pressure-test, internal
inspection devices, direct assessment, or alternative method) each high
risk segment.
By June 17, 2004, each operator must have begun its preparation to conduct
a baseline assessment on at least one high risk segment that the operator
has already identified. Preparing to conduct a baseline assessment means
that -
- an operator has scheduled for assessment the segments identified prior
to June 17, 2004; and
- an operator has started to contract or has entered into a contract with
a tool vendor to assess the identified segments; or
- an operator has started to assess the first scheduled segment.
PHMSA/OPS also considers that any of the following actions as meeting the
intent of the statute that an operator have begun the baseline integrity
assessment process by June 17, 2004. The following actions are not the
only actions that PHMSA/OPS will accept.
- an operator has installed launchers or receivers for internal inspection
devices;
- an operator has set up a segment for a pressure test; or
- an operator has completed the pre-assessment step for Direct Assessment.
II.
BACKGROUND
The Federal Pipeline Safety Statute (49 U.S.C.
60109 (c)) requires that PHMSA/OPS issue regulations, by December 17, 2003, establishing
requirements for integrity management programs for gas transmission pipelines
in high consequence areas. The statute also imposes requirements directly on
gas pipeline operators. The statute requires each gas pipeline operator to adopt
an integrity management program for pipeline segments located in high consequence
areas by December 17, 2004, and to begin the baseline integrity assessment of
those segments no later than June 17, 2004. The statute requires that an operator
complete the baseline assessment on all the operator’s gas transmission pipeline
segments in high consequence areas by December 17, 2012, with at least 50 percent
of those segments being assessed no later than December 17, 2006. An operator
must also reassess each of the segments every 7 years.
Trade associations that represent gas pipeline operators have requested guidance
on what actions are necessary for an operator to have begun the required baseline
assessment process by the statutory deadline. This advisory bulletin gives guidance
on the actions PHMSA/OPS expects an operator to take by June 17, 2004 for the
operator to be considered as having begun the baseline assessment.
On August 6, 2002, PHMSA/OPS published a final rule defining high consequence
areas i.e. those areas for which additional protections are required (67 FR
50824). PHMSA/OPS initiated the rulemaking on integrity management program requirements
with a notice of proposed rulemaking (NPRM), published January 28, 2003 (68
FR 4278), that proposed substantive requirements to establish integrity management
programs and modifications to the high consequence area definition to better
identify population potentially impacted by a pipeline failure. A final rule
has not yet been issued. PHMSA/OPS published an advisory bulleting on July 17,
2003 (68 FR 42456) providing guidance on steps PHMSA/OPS expects gas transmission
operators to take to determine “identified sites” along the pipeline, one of
the components of the high consequence area definition.
PHMSA/OPS expects that by June 17, 2004, an operator will have identified many
high consequence areas along its transmission pipelines though operation and
maintenance activities on the pipeline right-of-way, including patrolling, that
the operator conducts on a routine basis, and through the guidance PHMSA/OPS
provided on how to determine the identified sites component with the help of
emergency response officials. An operator will also have integrated all available
data and information the operator has available on those high consequence areas
to prioritize segments that are high risk, and to have begun selecting the assessment
method best suited for each segment and scheduling the assessment of the high
risk segments.
Issued in Washington, DC on _________________.
Stacey L. Gerard,
Associate Administrator for Pipeline Safety.
|