Rec. No. Issue Date Reference
|
Technical Category
|
OPEN NTSB Recommendation
|
NTSB Classification Actions and Actions Taken by Lead Agency |
Actions Needed |
Correspondence History PHMSA/NTSB
|
P-90-29
issued
10-01-90
|
Damage Prevention
|
Outstanding . With the assistance of the Minerals Management Service, U.S. Coast Guard, and U.S. Army Corps of Engineers, develop and implement effective methods and requirements to bury, protect, inspect the burial depth of, and maintain all submerged pipelines in areas subject to damage by surface vessels and their operations. |
Open – acceptable response . Study completed in January 1998. Final rule published on August 10, 2004. On August 17, 2004, PHMSA submitted a letter requesting closure. NTSB responded by encouraging PHMSA to conduct further studies on risks associated with offshore areas. OPS is evaluating other options. |
Complete additional evaluation. |
08-17-04
07-31-98 |
12-20-04
02-07-08
04-18-01
06-18-99 |
P-98-02 issued 04-30-98
|
Plastic Pipe
|
Outstanding . Determine the extent of the susceptibility to premature brittle-like cracking of older plastic piping that remains in use for gas service nationwide. |
Open – acceptable response . The Plastic Pipe Database Committee, with representatives from PHMSA, NTSB, American Gas Association, American Public Gas Association, Plastics Pipe Institute, Gas Research Institute, industry and the states, continue to collect data on in-service plastic piping material failures. Data collection will continue until January 2006. |
Complete data collection and analysis. |
12-11-02
03-17-99 |
03-17-03
07-13-00
11-15-99 |
P-99-12 issued
06-01-99
Fatigue Report
|
Fatigue
(Hours of Service)
|
Establish within 2 years scientifically based hours-of-service regulations that set limits on hours of service, provide predictable work and rest schedules, and consider circadian rhythms and human sleep and rest requirements. |
Open – acceptable response . PHMSA continues its assessment of human fatigue in pipeline operations in a variety of research and standards efforts. The study results are expected in June 2006. PHMSA published guidance in advisory bulletin ADB-05-06 (70 FR 46917; August 11, 2005). PHMSA is await NTSB feedback on P-98-30 and results of its study. |
Complete study and amend regulation, as necessary, based on study results. |
11-04-04
04-02-02
09-07-99 |
04-27-05
06-28-02
04-18-01
10-15-99
|
P-01-02 issued 06-22-01
South Riding
|
Pipeline Technology
(Excess Flow Valves) |
Require that excess flow valves be installed in all new and renewed gas service lines, regardless of a customer’s classification, when the operating conditions are compatible with readily available valves. |
Open – acceptable response . PHMSA is considering incorporating requirements for these valves in the upcoming integrity management rule for gas distribution pipeline. NTSB does not agree with that approach. Public meetings were held on June 17 and September 22, 2005, to discuss the use of these valves in gas distribution pipelines. The results of the meetings will be presented to the technical advisory committees at meetings scheduled for December 13 & 14, 2005. |
Amend regulations, as necessary. |
09-03-04
04-23-02
07-16-01
|
11-29-04
06-14-02
|
P-03-01 issued 02/27/03
Carlsbad
|
Pipeline Technology
(Internal Corrosion)
|
Revise regulations to require that new or replaced pipelines be designed and constructed with features to mitigate internal corrosion. |
Open – acceptable response . PHMSA is preparing an NPRM and expects to publish it in November 2005. |
Issue final rule. |
08-15-03 |
11-21-03 |
P-04-01 issued 07/01/04
Cohasset
|
Pipeline
Intergrity
|
Remove the exemption in regulations that permits pipe to be placed in natural gas service after pressure testing when the pipe cannot be verified to have been transported in accordance with the American Petroleum Institute’s (API) recommended practice RP5L1. |
Open – acceptable response .
PHMSA plans to explore the technical feasibility of removing the exemption or other alternative action. This notice will also address recommendations P-04-02 and P-04-03.
|
Conduct technical study. |
09-23-04 |
12-20-04 |
P-04-02 issued 07/01/04
Cohasset
|
Pipeline
Intergrity |
Amend regulations to require that natural gas pipeline operators and hazardous liquid operators follow API-recommended practice for transportation of pipe on marine vessels. |
Open – acceptable response . PHMSA plans to explore the technical feasibility of removing the exemption or other alternative action. This notice will also address recommendations P-04-02 and P-04-03. |
Conduct technical study. |
09-23-04 |
12-20-04 |
P-04-03 issued 07/01/04
Cohasset
|
Pipeline
Intergrity |
Evaluate the need for a truck transportation standard to prevent damage to pipe and, if needed, develop the standard and incorporate it into regulations for both natural gas and hazardous liquid line pipe. |
Open – acceptable response . PHMSA plans to explore the technical feasibility of removing the exemption or other alternative action. This notice will also address recommendations P-04-02 and P-04-03. |
Conduct technical study. |
09-23-04 |
12-20-04 |
| P-05-01 issued 12-23-05 |
Pipeline Technology (SCADA screens) |
NTSB recommends that PHMSA require operators of hazardous liquid pipelines to follow the American Petroleum Institute's Recommended Practice 1165 for the use of graphics on the Supervisory Control and Data Acquisition (SCADA) screens. |
NTSB Classification: Open, acceptable response |
none |
08-08-06 04-26-06 |
none |
| P-05-02 issued 12-23-05 |
|
NTSB recommends that PHMSA require pipeline companies to have a policy for the review/audit of alarms. |
NTSB Classification: Open, acceptable response |
none |
08-08-06 04-26-06 |
none |
| P-05-03 issued 12-23-05 |
Pipeline Technology
(leak events) |
NTSB recommends that PHMSA require controller training to include simulator or non-computerized simulations for controller recognition of abnormal operating conditions, in particular, leak events |
NTSB Classification: Open, acceptable response |
none |
08-08-06 04-26-06 |
none |
| P-05-04 issued 12-23-05 |
Fatigue (liquid accident reporting form) |
NTSB recommends that PHMSA change the liquid accident reporting form (PHMSA F 7000-1) and require operators to provide data related to controller fatigue. |
NTSB Classification: Open, acceptable response |
none |
08-08-06 04-26-06 |
none |
| P-05-05 issued 12-23-05 |
Pipeline Technology |
NTSB recommends that PHMSA require operators to install computer-based leak detection systems on all lines unless engineering analysis determines that such a system is not necessary. |
NTSB Classification: Open, acceptable response |
none |
08-08-06 04-26-06 |
none |
P-07-7
06/25/07
|
Operator Regulations |
The National Transportation Safety Board recommends that the Pipeline and Hazardous Materials Safety Administration: Require in 49 Code of Federal Regulations 195.52 that a pipeline operator must have a procedure to calculate and provide a reasonable initial estimate of released product in the telephonic report to the National Response Center. |
NTSB Classification: Open |
Address Recommendation |
|
06-25-07
10-23-07 |
P-07-08
|
Emergency Response |
The National Transportation Safety Board recommends that the Pipeline and Hazardous Materials Safety Administration: Require in 49 Code of Federal Regulations 195.52 that a pipeline operator must provide an additional telephonic report to the National Response Center if significant new information becomes available during the emergency response. |
NTSB Classification: Open |
Address Recommendation |
|
06-25-07
10-23-07 |
P-07-09
|
Pipeline Integrity |
The National Transportation Safety Board recommends that the Pipeline and Hazardous Materials Safety Administration: Require an operator to revise its pipeline risk assessment plan whenever it has failed to consider one or more risk factors that can affect pipeline integrity. |
NTSB Classification: Open |
Address Recommendation |
|
06-25-07
10-23-07 |