
RSPA Actions Taken in Response to the Olympic Pipeline Accident in Bellingham, Washington
(August 7, 2001):

In the wake of the Bellingham, Washington
accident on June 10, 1999, PHMSA has taken the following actions:
June 11, 1999,
initial response by PHMSA's Office of Pipeline Safety (OPS) personnel.
Subsequently dispatched four investigators to the site to assist in the incident
response and accident investigation. PHMSA investigators are closely
collaborating with the NTSB to determine the cause of the accident, and identify
any pipeline safety violations.
June 18, 1999, PHMSA issued a corrective action order (CAO) to Olympic. The order requires
Olympic to conduct tests and evaluations, as well as make hardware improvements,
e.g. valves, SCADA, before the pipeline can be put back into service. PHMSA will
not allow the pipeline to return to service until all safety issues are
adequately addressed.
July 7, 1999, PHMSA issued an alert notice to the pipeline industry regarding potential SCADA
problems that may affect their pipeline system. The alert notice was based on
early accident findings which identified improper SCADA performance as a major
contributor to the Bellingham accident. Similar SCADA-related occurrences on
other pipeline facilities were subsequently identified, thereby resulting in our
industry wide advisory.
July 23, 1999, PHMSA retained a third party, nationally recognized analyst to review the
internal inspection logs to independently assess anomalies identified on the
Olympic pipeline system.
August 10, 1999, PHMSA issued an amended corrective action order. The amendment requires Olympic
to report all anomalies with their SCADA system for a period of one (1) year;
within 3 months, develop and implement a training program for controllers
specific to the SCADA system in use and review the qualifications of each
controller to perform his/her job; perform a design review of then Ferndale to
Allen segment to insure that station safety devises will shut down the segment
within applicable parameters including performing a worst case surge analysis,
testing all relief valves for reliable operation, and performing a design review
of the Bayview Products Terminal; after running any internal inspection devices,
excavate and examine any anomaly identified in the top half of the pipe and take
remedial action with respect to each; consider the possibility of internal
corrosion in reviewing results of internal inspection device surveys; review
existing procedures for normal, abnormal, and emergency operations of the
Ferndale to Allen segment and make any necessary changes to ensure that they
address operations at the Bayview Products Terminal.
August 15, 1999, PHMSA stationed permanent pipeline inspector in Olympia, Washington.
September 19 - 25, 1999,
Olympic hydrostatically tested the 16-inch pipeline through the City of
Bellingham. One failure occurred on pre-1970 ERW pipe manufactured by Lone Star.
September 24, 1999, PHMSA issued a second amended corrective action order. Required Olympic to drop
operating pressures in entire system to 80% MOP, conduct hydrotest of Ferndale
to Allen & all pre-1970 low frequency ERW pipe, conduct internal inspections,
and report findings of management audit within 6 months of completion.
October 8 - 29, 1999,
Olympic hydrostatically tested the 16-inch Ferndale to Allen pipeline segment
from Milepost 0 - 12 and Milepost 22 - 40.
January 14, 2000,
Olympic requests permission to re-start the 16-inch Ferndale to Allen pipeline
segment.
January 26, 2000, PHMSA correspondence to Olympic requesting implementation plans for Valve Study
and In-line Inspection Surveys.
March 9, 2000, PHMSA correspondence concerning inadequacies and omissions in Olympic's
implementation plans & procedures for re-start of the 16-inch Ferndale to Allen
pipeline segment.
Spring of 2000,
Olympic completed the mandated corrective actions for enhanced valve placement,
SCADA enhancements, controller training, and overpressure protection.
June 2, 2000, PHMSA proposed a $3.05 million civil penalty against Olympic Pipeline, for safety
violations related to the June 10, 1999 pipeline failure. Each of the penalties
proposed carries the maximum fine allowed under current pipeline safety law.
June 8, 2000, PHMSA announced a partnership between the State of Washington and the Office of
Pipeline Safety that will allow Washington State pipeline safety inspectors to
participate in inspections of interstate pipeline facilities.
July 1, 2000,
the operation of the Olympic Pipeline was transferred from Equilon to British
Petroleum (BP).
August 3, 2000,
Olympic completed the Geometry and High Resolution Magnetic Flux Leakage surveys
for the entire pipeline system.
August 4, 2000, PHMSA tentatively accepted proposed integrity management actions by BP Amoco,
owner of Olympic Pipe Line, to further ensure the safety of their pipeline
system in the State of Washington. In addition to conducting hydrostatic testing
of the 16-inch pipeline from Allen to Renton, Washington, the company plans to
use the state-of-the-art transverse field inspection tool to identify seam-weld
and other potential longitudinal defects on their entire 400-mile pipeline
system.
August 8, 2000, PHMSA held a public meeting in Bellingham. The meeting gave the public an
opportunity to learn more about the results of the internal inspection tests
taking place on the 16-inch pipeline from Ferndale to Allen and other completed
mandated safety improvements.
August 18, 2000,
Olympic completed replacement of the portion of the pipeline adjacent to the
Kulsham Middle School in the City of Bellingham, Washington.
August 25, 2000, PHMSA's correspondence to Olympic, stating prior to allowing resumed operation at
reduced pressure of the shutdown 16-inch pipeline segment, OPS needs added
assurance the management, procedural, and organizational issues playing a role
in the accident have been adequately resolved. The company was provided with a
list of key issues to be reviewed by OPS as part of the management audit.
October 31, 2000, PHMSA's correspondence approving the final excavation list, evaluation and repair
criteria for the Olympic 16-inch Pipeline.
November 9, 2000,
OPS conducted a review of management, procedural, and organizational issues
playing a role in the accident. The review provided OPS with additional
assurances necessary regarding BP's operation of the Olympic Pipe Line System.
November 28, 2000,
Repairs complete for the Cherry Point to Allen segment of 16-inch pipeline. OPS
and WUTC personnel continuously monitored evaluation and repair activities for
this pipeline segment from May through November of 2000.
December 5, 2000,
Repairs complete for the Anacortes to Allen segment of 16-inch pipeline.
December 7, 2000, PHMSA's correspondence granting Olympic permission to purge the 16-inch Cherry
Point to Allen pipeline segment with nitrogen. The nitrogen purge removed
residual diesel from ILI activities and oxygen from repair activities
eliminating the possibility of a combustible atmosphere forming within the
pipeline. The nitrogen purge also provided for a low pressure leak test of the
pipeline's integrity.
January 25, 2001, PHMSA's correspondence to Olympic allowing introduction of product into the
Cherry Point to Ferndale and Ferndale to Allen pipeline segments.
February 7, 2001, PHMSA's correspondence to Olympic allowing limited operation of the Cherry Point
to Ferndale and Ferndale to Allen pipeline segments.
February 8, 2001,
Olympic resumed limited operation of the Cherry Point to Allen segment of
pipeline. This segment had not been operated, except for ILI surveys, since the
June 10, 1999, incident in Bellingham, Washington. Prior to and during the
restart of the pipeline segment OPS and WUTC personnel reviewed procedures and
observed pipeline operations assuring the operating integrity of the pipeline
system.
May 16, 2001,
Olympic successfully completed the voluntary hydrostatic testing of the 16-inch
Allen to Renton pipeline segment. The OPS and WUTC personnel observed the
pressure testing of the pipeline segment and reviewed test documentation.
June 3, 2001,
Olympic resumed limited operation of the 16-inch Allen to Renton pipeline
segment. This segment had not been operated, except for ILI surveys, since the
June 10, 1999, incident in Bellingham, Washington. Prior to and during the
restart of the pipeline segment OPS and WUTC personnel reviewed procedures and
observed pipeline operations assuring the operating integrity of the pipeline
system.
June 2001 to Present,
OPS and WUTC continue observing the evaluation and repairs of the Allen to
Renton 16-inch pipeline segment. Two sites, due to permitting constraints,
remain to be evaluated on the 16-inch pipeline segment. The two sites have been
successfully pressure tested and the pipeline's operating pressure remains
restricted. OPS and WUTC continue to monitor evaluation and repair activities
associated with the other pipeline segments voluntarily surveyed by BP.
LAST UPDATE 08/07/2001
|