Integrity Actions by Line Segment:

Develop and follow written procedures for conducting
internal inspections to include fitness for service criteria for identifying,
prioritizing, and correcting defects. The procedures shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G.(CAO
2nd Amendment Item 23)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to CAO Item 5)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by BP Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by BP Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by BP Outline of Integrity Management Plan)
Complete the analysis of internal inspection data
and any remedial actions for anomalies that affect pipeline integrity within six
months of completion of an internal inspection. The analysis shall include a
comparison of metal loss with pipe deformation. (CAO 2nd Amendment
Item 23)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (June 22,
2000, letter to Olympic from OPS)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to CAO Item 5)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by BP Outline of Integrity Management Plan)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this
item.(CAO 2nd Amendment Item 24)
Ferndale
to Allen 16-inch: TOP
Restrict the maximum operating pressure to 1056
psig which is 80 percent of the normal operating pressure or 80 percent of the
surge pressure at the point of failure, whichever is lower. After the hazard has
been abated OPS can remove the pressure restriction by written approval to
Olympic. (CAO 1st Amendment Item7)
Obtain written approval and implement a plan with
corrective measures addressing factors playing a role in the June 10, 1999,
incident. (CAO Item 1)
Prior to undertaking any testing, repairs, or
construction needed to prepare for the return of the pipeline to service or for
a rerouting of the pipeline, notify the Director, Western Region, and submit
plans and testing or repairs or comprehensive construction specifications unless
told by the Director that it is not necessary in a particular situation. (CAO 2nd
Amendment Item 18)
Conduct hydrostatic pressure testing of line
between mileposts 12 and 22 which includes the June 10, 1999, rupture site. (Olympic's
July 26, 1999, response plan to CAO Item 5)
Conduct hydrostatic pressure testing at a test
pressure of 90 percent of Specified Minimum Yield Strength for a minimum period
of eight hours and metallurgically test any failure that occurs in a manner
which will identify the cause of failure including possible cyclic fatigue. If
during the pressure testing a failure occurs on line pipe which was manufactured
by Lone Star, evaluate the need to pressure test the remainder of the Olympic
Pipeline System. The evaluation must take into account the failure mode, the
characteristics of the pipe, the pressure at the time of failure, the existence
of other alternative assurances of integrity, and other factors relevant to a
decision of the risk of a similar failure. (CAO 2nd Amendment Items
20 & 21)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (Voluntary Action by BP Outline of Integrity
Management Plan - March 9th letter not applicable as section has
experienced hydrostatic test since June 10, 1999, incident).
Conduct an annual deformation tool survey
(Voluntary Action by BP Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by BP Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by BP Outline of Integrity Management Plan)
Complete the analysis of internal inspection data
and any remedial actions for anomalies that affect pipeline integrity within six
months of completion of an internal inspection. The analysis shall include a
comparison of metal loss with pipe deformation. (CAO 2nd Amendment
Item 23)
Excavate and repair anomalies noted by the OPS
internal inspection consultant from review of the 1991 and 1996, low resolution
magnetic flux leakage tool and the 1997 caliper tool surveys. Provide OPS with
the disposition of each anomaly from these surveys. (OPS September 16, 1999,
letter to Olympic)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (June 22,
2000, letter to Olympic from OPS)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO)
Test mainline valves intended to isolate sections
of the pipeline traversing populated and environmentally sensitive areas and
take any needed remedial action to assure they will perform their intended
function. (CAO Item 3)
Install a check valve adjacent to the Lakeway
Drive block valve at milepost 16.22. (CAO Item 4)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Perform a design review to ensure the station
safety devices will shut the segment down within applicable parameters. This
review will include at least the following (CAO 1st Amendment Item
14):
- A surge analysis using the worst case
scenario, i.e. highest flow rates using drag reducing agent with the
shortest possible valve closure times and highest density product.
- A test of the relief valves to determine
that capacity is adequate and each valve operates reliably.
- A design review of the physical piping in
the Bayview Products Terminal that includes the interaction of all station
safety devices.
Conduct a Cycle-Stress Analysis (Voluntary Action
by BP Outline of Integrity Management Plan)
Review existing procedures for normal, abnormal,
and emergency operations and make any necessary changes to ensure that they
address operations at the Bayview Products Terminal. (CAO 2nd
Amendment Item 17)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Allen to Renton 16-inch:
Restrict the maximum operating pressure of this
segment to 80 percent of its normal operating pressure or 80 percent of the
surge pressure at the point of failure, whichever is lower. After the hazard has
been abated OPS can remove the pressure restriction by written approval to
Olympic. (CAO 2nd Amendment Item 9)
Obtain written approval and implement a plan with
corrective measures addressing factors playing a role in the June 10, 1999,
incident. (CAO Item 1)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by BP Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by BP Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by BP Outline of Integrity Management Plan)
Complete the analysis of internal inspection data
and any remedial actions for anomalies that affect pipeline integrity within six
months of completion of an internal inspection. The analysis shall include a
comparison of metal loss with pipe deformation. (CAO 2nd Amendment
Item 23)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic)
Pressure test sections constructed of pre-1970
ERW pipe manufactured by Lone Star. The locations to be tested are: MP 42, Britt
Slough (77 feet & 377 feet), MP 55.9, Pilchuck Creek crossing (968 feet); MP
57.4, Stillaguamish River crossing (624 feet); MP 77.8, South of the Snohomish
River crossing (368.6 feet). (CAO 2nd Amendment Item 20)
Pressure test sections constructed of pre-1970
ERW pipe manufactured by Kaiser. The locations to be tested are: MP 41-42,
Skagit River (1,215 feet); MP 78, Snohomish River (525 feet). (Olympic is
conducting voluntary testing per February 29, 1999, letter from Olympic)
Conduct a hydrostatic test of the Allen to Renton
line segment to the pipeline safety requirements and conduct TFI internal
inspection after the pressure testing. (Voluntary Action by BP Outline of
Integrity Management Plan)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Perform a design review to ensure the station
safety devices will shut the segment down within applicable parameters. This
review will include at least the following (CAO 2nd Amendment Item
14):
- A surge analysis using the worst case
scenario, i.e. highest flow rates using drag reducing agent with the
shortest possible valve closure times and highest density product.
- A test of the relief valves to determine
that capacity is adequate and each valve operates reliably.
- A design review of the physical piping in
the Bayview Products Terminal that includes the interaction of all station
safety devices.
Conduct a Cycle-Stress Analysis (Voluntary Action
by BP Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Anacortes
to Allen 16-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Pressure test sections constructed of pre-1970
ERW pipe manufactured by Lone Star. MP 2.8, Swinomish Slough crossing (906.9
feet). (CAO 2nd Amendment Item 20)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by BP Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by BP Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by BP Outline of Integrity Management Plan)
Complete the analysis of internal inspection data
and any remedial actions for anomalies that affect pipeline integrity within six
months of completion of an internal inspection. The analysis shall include a
comparison of metal loss with pipe deformation. (CAO 2nd Amendment
Item 23)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by BP Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Allen
to Renton 20-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic -
Voluntary Action by Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Renton
to Seattle 12-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic -
Voluntary Action by Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Renton
to SeaTac 12-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic -
Voluntary Action by Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Vancouver
Junction to Vancouver Delivery Facility 12-inch:
TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic -
Voluntary Action by Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Renton
to Portland 14-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an internal inspection utilizing the
transverse field inspection (TFI) device for all segments of pipe not subjected
to a successful hydrostatic test, meeting the pipeline safety requirements,
since the June 10, 1999, incident. (OPS March 9, 2000, letter to Olympic -
Voluntary Action by Olympic).
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Tacoma
Junction to Tacoma Delivery Facility 8-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
Olympia
Junction to Olympia Delivery Facility 6-inch: TOP
Maintain normal operating pressure not to exceed
80 percent of the maximum operating pressure. Olympic may request an increase in
operating pressure accompanied by a written document demonstrating the segment
can be operated safety at the increased pressure. (CAO 2nd Amendment
Item 19)
Develop and follow written procedures for the
conduct of internal inspections that includes fitness for service criteria for
identifying, prioritizing, and correcting defects. These shall include criteria
for deciding on direct pipeline examination, further integrity assessment, and
corrective measures including repair, replacement, or operational restrictions.
At a minimum, consider the criteria established in ASME B31-4 and ASME B31-G. (CAO
2nd Amendment Item 23 - Voluntary Action by Olympic)
In conducting internal inspections select
internal inspection devices that can accurately detect metal loss, pipe
deformation, and enable strain calculation to be conducted. (CAO 2nd
Amendment Item 23 - Voluntary Action by Olympic)
Conduct internal inspection survey utilizing best
technology incorporating a high resolution magnetic flux leakage tool and a
deformation tool. (Olympic's July 26, 1999, response plan to Item 5 CAO -
Voluntary Action by Olympic)
In conducting any internal inspection excavate
and visually examine any anomaly that could be associated with excavation damage
which is identified in the top half of the pipe, and take appropriate remedial
action with respect to each. (CAO 1st Amendment Item 15 - Voluntary
Action by Olympic)
In conducting any internal inspection consider
the possibility of internal corrosion in conducting the inspection and in
analyzing the results. (CAO 1st Amendment Item 16 - Voluntary Action
by Olympic)
Conduct an annual deformation tool survey
(Voluntary Action by Olympic Outline of Integrity Management Plan)
Schedule survey of high resolution magnetic flux
leakage tool 3 years after TFI (Voluntary Action by Olympic Outline of Integrity
Management Plan)
Conduct Integrity Assessment Program drive Risk
Assessment (Voluntary Action by Olympic Outline of Integrity Management Plan)
Make pipeline repairs in accordance with a
conservative application of the ASME B31.4 Code for Pressure Piping. (OPS June
22, 2000, letter to Olympic - Voluntary Action by Olympic)
Review the Supervisory Control and Data
Acquisition System (SCADA) to determine the cause of the deficiencies that
occurred on June 10, 1999, and correct these deficiencies. (SCADA improvements
affect the entire pipeline system CAO Item 2)
Before November 10, 1999, complete the following
with respect to persons involved with controlling the operations of the pipeline
through the SCADA system (CAO 1st Amendment Item13):
- Develop and implement a training program
for controllers specific to the SCADA system in use that includes responding
to abnormal operations and starting up and shutting down any part of the
pipeline system.
- In addition to the training, review the
qualifications of each controller to perform his or her duties and to
recognize conditions that are likely to cause emergencies and be able to
predict the consequences of facility malfunctions or failures such as those
that occurred on June 10, 1999.
- Provide specific, specialized, technical
training to controller personnel responsible for maintenance and operation
of the hardware and software components of the SCADA systems.
- Review the qualifications of the personnel
responsible for maintenance and operation of hardware and software
components of the SCADA systems to assure that they can perform the
functions needed.
- In training provided under this item,
include classroom and practical exercises and use of a pipeline simulator as
appropriate.
For a minimum period of one (1) year after the
last change, required by the orders review, to the SCADA system has been
completed, monitor the operations of the SCADA system for anomalies in the
operations including, but not limited to, all processing errors, computer slow
downs, unintended defaults to the backup computer system, and communication
failures. Report each anomaly in writing to the Director, Western Region OPS
within 2 weeks of its occurrence. (CAO 1st Amendment Item12)
Conduct MARMAC Engineering and Design review of
mainline block valves and check valve spacing and effectiveness relative to
elevation, population, and environmentally sensitive areas. (Olympic's July
26, 1999, response plan to Item 5 CAO - Voluntary Action by Olympic)
Review of station discharge control and case
shutdown for maximum allowable operating pressure. (Overpressure Derivation
Documentation Review - Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct full flow test of all surge relief
valves. (Voluntary Action by Olympic July 26, 1999 response to CAO)
Conduct a surge analysis. (Voluntary Action by
Olympic July 26, 1999 response to CAO)
Conduct a Cycle-Stress Analysis (Voluntary Action
by Olympic Outline of Integrity Management Plan)
Within 6 months of completion of the management
audit provide for in the City Agreement, implement any corrective measures that
cover matters regulated in 49 CFR Part 195 and report progress on the
implementation to the Regional Director periodically, but no less frequently
than every three months. As the management audit nears completion, Respondent
may request that OPS specify which corrective actions are subject to this item.
(CAO 2nd Amendment Item 24)
LAST UPDATE 04/17/2001
|