
Advisory Bulletin:

OPS issued an advisory bulletin
to all pipeline operators to increase awareness of potential operational
limitations associated with Supervisory Control and Data Acquisition (SCADA)
systems and the possibility of those problems leading to or aggravating pipeline
releases.
PIPELINE SAFETY ADVISORY BULLETIN
ADVISORY BULLETIN: ADB-99-03 Date: July 7, 1999
To: Owners and Operators of Hazardous Liquid and Natural Gas Pipeline Facilities
Subject: Potential Service Interruptions in Supervisory Control and Data Acquisition Systems
Purpose: Inform pipeline system owners and operators of potential operational limitations
associated with Supervisory Control and Data Acquisition (SCADA) systems and the possibility
of those problems leading to or aggravating pipeline releases.
Advisory: Each pipeline operator should review the capacity of its SCADA system to ensure
that the system has resources to accommodate normal and abnormal operations on its pipeline
system. In addition, SCADA configuration and operating parameters should be periodically
reviewed, and adjusted if necessary, to assure that the SCADA computers are functioning as
intended. Further, operators should assure system modifications do not adversely affect overall
performance of the SCADA system. We recommend that the operator consult with the original
system designer.
Background: During an Office of Pipeline Safety (OPS) investigation of a recent pipeline
incident, OPS inspectors identified inadequate SCADA performance as an operational safety
concern. Immediately prior to and during the incident, the SCADA system exhibited poor
performance that inhibited the pipeline controllers from seeing and reacting to the development
of an abnormal pipeline operation.
Preliminary review of the SCADA system indicates that the processor load (a measure of
computer performance utilization) was at 65 to 70 percent during normal operations.
Immediately prior to an upset condition occurring on the pipeline, the SCADA encountered an
internal database error. The system attempted to reconcile the problem at the expense of other
processing tasks. The database error, coupled with the increased data processing burden of the
upset condition, hampered controller operations. In fact, key operator command functions were
unable to be processed immediately prior to and during the abnormal operation. It is possible
that post installation modifications may have hampered the system's ability to function
appropriately.
The combination of the database error, the inadequate reserve capacity of the SCADA processor,
and the unusually dynamic changes that occurred during the upset condition, appear to have
combined and temporarily overburdened the SCADA computer system. This may have
prevented the pipeline controllers from reacting and controlling the upset condition on their
pipeline as promptly as would have been expected. For further information, contact Chris
Hoidal, Director, OPS Western Region at 303-231-5701.
|